NE 48th Street Extension

The extension of NE 48th Street opened the final phase of development at Hunt Midwest Business Center, connecting the road’s existing access to Interstate 435 east to N Arlington Avenue and completing the road network across the 2,500-acre megasite.

The $16.3 million project also included the construction of a new 300-foot-long, three-span precast concrete bridge and more than three quarters of a mile of new water mains.

The new road and water connections will support construction on the final phase of Hunt Midwest Business Center, already underway, including about 2.6 million square feet of additional Class A industrial space and a new north entrance to SubTropolis, the world’s largest underground business complex located directly below the business center.

Infrastructure Featured-Infrastructure Completed
2024 YEAR COMPLETED
$16.3 million PROJECT COST

  • $16.3 million project cost
  • 300-foot, three-span precast concrete bridge
  • Completed 2013

  • City of Kansas City, Missouri
Senior Manager of Project Management Terry Owens is responsible for the design and development of home sites in Hunt Midwest’s new home communities across the Kansas City metro and manages the company’s public and private infrastructure projects.